25.1 Objective 7: Release FY 24 Program Plan updates #150
Comments
Schedule change for SNWG MO Program Plan update - target approval
Generated by QuickGit from 2024-09-03 SNWG MO Internal Planning Meeting |
Program Plan - Jenny may send out follow-up questions to the team this week to get confirmation on necessary updates. Generated by QuickGit from 2024-09-09 SNWG MO Internal Planning Meeting |
Generated by QuickGit from 2024-09-16 SNWG MO Internal Planning Meeting |
SNWG MO Program Plan - meeting with Jenny/Sean to discuss progress and SNWG MO audit driven updates
Generated by QuickGit from 2024-09-23 SNWG MO Internal Planning Meeting |
Program Plan - remaining items:
Generated by QuickGit from 2024-10-15 SNWG MO Internal Planning Meeting |
Program Plan - remaining items:
Generated by QuickGit from 2024-10-21 SNWG MO Internal Planning Meeting |
Program Plan - remaining items:
Generated by QuickGit from 2024-10-28 SNWG MO Internal Planning Meeting |
program plan
Generated by QuickGit from 2024-11-04 SNWG MO Internal Planning Meeting |
prog plan
Generated by QuickGit from 2024-11-12 SNWG MO Internal Planning Meeting |
SNWG MO Project Plan sent out for re-review. Most changes since last review occurred in Section 2 (Goals, Objectives, and Metrics). Generated by QuickGit from 2024-11-25 SNWG MO Internal Planning Meeting |
Received feedback from HQ regarding the SNWG MO Project Plan. Currently plan to split up into 3 documents:
Generated by QuickGit from 2024-12-02 SNWG MO Internal Planning Meeting |
Working on HQ-MO project plan
Generated by QuickGit from 2024-12-09 SNWG MO Internal Planning Meeting |
more work to do for revisions; push to future PI Planning |
SNWG MO Project Plans: 10-page(ish) project plan for HQ (streamlined, lightweight version of current Project Plan, top priority) Generated by QuickGit from 2025-01-27 SNWG MO Internal Planning Meeting |
Summary
Acceptance Criteria:
Tasks
Dependencies
Risks
Future PI